Hi All,
We have a 2 node cluster running SQL Server 2000 on Windows 2000 which
needs replacing. The nature of our business is 24 hour operation, so
the downtime to do such needs to be as small as possible.
We have a new cluster ready and waiting in our data centre that is
built on Windows 2003 with SQL Server 2000.
Our issues are:
=B7Configuring all the applications to the new Cluster Name / IP
Address - In the past we have found things hard-coded
=B7Migrate all the data (~100GB) over to the new MSA
=B7Smallest downtime possible
The idea's we have come up with already are:
=B7Frigg DNS to point the old cluster name to the new cluster name and
then migrate all the applications to the new name as time permits.
=B7Rename the new nodes as <NAME>3/4 and add these into the existing
cluster; however the MSA is directly connected to Nodes 1/2.
=B7Remove 1 node from the old cluster, add a new node in, fail-over to
new node, remove 2nd old node, add new node, however I'm thinking
this may not work?
Another consideration is that we use SecurePath on the MSA's so this
could be a PITA.
Does anyone have any other suggestions which we could consider?
Thanks
Well, since you asked.
You could do a minimally disruptive replacement by replacing each node with
one of the new nodes. Uninstall SQL from the "other" node, evict the node,
add the node, run the SQL nstaller to install and configure SQL on the new
node. Wait for maintenance window and do a failover test. Repeat with the
other node.
The other process I use to migrate systems is to run a custom log ship
script (they aren't that hard to write, google will point to some nice free
examples.) to get them ready. Do a final log backup and put the old
databases into norecovery mode. Do a final catch up and go live on the new
system. Patch DNS (hint, use the SRV record type). and go. I can switch
over a typical server with 10-30 databases with less than 10 minutes of
downtime this way.
Geoff N. Hiten
Senior Database Administrator
Microsoft SQL Server MVP
"Steve" <SMaxwell@.NationalExpress.com> wrote in message
news:1160476240.405910.76230@.e3g2000cwe.googlegrou ps.com...
Hi All,
We have a 2 node cluster running SQL Server 2000 on Windows 2000 which
needs replacing. The nature of our business is 24 hour operation, so
the downtime to do such needs to be as small as possible.
We have a new cluster ready and waiting in our data centre that is
built on Windows 2003 with SQL Server 2000.
Our issues are:
Configuring all the applications to the new Cluster Name / IP
Address - In the past we have found things hard-coded
Migrate all the data (~100GB) over to the new MSA
Smallest downtime possible
The idea's we have come up with already are:
Frigg DNS to point the old cluster name to the new cluster name and
then migrate all the applications to the new name as time permits.
Rename the new nodes as <NAME>3/4 and add these into the existing
cluster; however the MSA is directly connected to Nodes 1/2.
Remove 1 node from the old cluster, add a new node in, fail-over to
new node, remove 2nd old node, add new node, however I'm thinking
this may not work?
Another consideration is that we use SecurePath on the MSA's so this
could be a PITA.
Does anyone have any other suggestions which we could consider?
Thanks
Showing posts with label node. Show all posts
Showing posts with label node. Show all posts
Wednesday, March 28, 2012
Monday, March 26, 2012
migrating a SQL Cluster to new hardware
I need your advise on migrating a two node SQL 2000 cluster to new hardware
including servers and disks.
thanks.
Amila
Create a new cluster with the new hardware, install a SQL instance, and then
migrate the databases over to the new instance (e.g. following steps in
http://vyaskn.tripod.com/moving_sql_server.htm and its referenced articles).
If the shared drives are presented from a SAN, you can remove the drives
from the cluster, create a new cluster, install a SQL instance in exactly the
same way as the existing SQL instance, and present the shared drives to the
new cluster.
If you can afford the downtime, and want to keep the server names, you can
remove the shared drives (LUNs), deactivate the cluster nodes, create a new
cluster with the same node names, cluster names, and virtual server names,
install a SQL instance, and present the same LUNs to the new cluster. The new
SQL instance can come up exactly the same as the previous one.
You may also try to perform the so-called rolling upgrade, i.e. upgrade one
node to new hardware a time.
Which method to choose depends on your upgrade requirements.
Linchi
"Amila chandrasekera" wrote:
> I need your advise on migrating a two node SQL 2000 cluster to new hardware
> including servers and disks.
>
> thanks.
> Amila
>
>
|||We have done both of what Linchi suggested: new system build/disk migration
versus node rebuild/upgrade.
The new cluster build is cleaner/easier, but then your applications have to
be migrated to the new host name (unless you can incur the long outage).
The node rebuild/upgrade is not quite as clean, but it minimizes the impact
to your end users.
Check out the maintenance and troubleshooting sections of the following
guide. There is also a link at the top that directs you to the 2005 doc as
well. Read both.
http://www.microsoft.com/technet/prodtechnol/sql/2000/maintain/failclus.mspx#E14AG
The short sequence is:
Uninstall passive node from the sql server setup.
Evict passive node from cluster administrator.
Rebuild passive node.
Join rebuilt node through cluster administrator.
Install rebuilt node to sql server setup.
Patch sql server rebuilt node to current patch + hotfix as active node.
Move over resources and repeat for each cluster node.
Sincerely,
Anthony Thomas
"Amila chandrasekera" <achandra@.insight.com> wrote in message
news:%23h6t5u7SHHA.412@.TK2MSFTNGP02.phx.gbl...
> I need your advise on migrating a two node SQL 2000 cluster to new
hardware
> including servers and disks.
>
> thanks.
> Amila
>
|||Run upgrade advisor to detect upgrade issues, run checkdb on the databases
on the clusters, detach them, copy them (do not move them) to the new
cluster, attach them, run checkdb, update statistics, back them up. Migrate
all dependencies (logins, jobs, extended stored procedures, com objects and
file paths).
Check all functionality on the new cluster. Roll back if you have to by
reattaching the existing database on the old cluster.
repoint the client applications.
You might want to review all methods to do this in the
http://download.microsoft.com/download/1/6/c/16c0ec7a-bb53-4aea-9020-cb2f80424322/SQL2005UpgradeTechRef.doc
Hilary Cotter
Looking for a SQL Server replication book?
http://www.nwsu.com/0974973602.html
Looking for a FAQ on Indexing Services/SQL FTS
http://www.indexserverfaq.com
"Amila chandrasekera" <achandra@.insight.com> wrote in message
news:%23h6t5u7SHHA.412@.TK2MSFTNGP02.phx.gbl...
>I need your advise on migrating a two node SQL 2000 cluster to new hardware
>including servers and disks.
>
> thanks.
> Amila
>
|||Thanks for the replies so far. This migration is from SQL 2000 to SQL 2000
(both source and target are running on Windows 2003 Advanced server). I am
not planning to do a SQL 2005 upgrade with this migration. It is purely a
hardware upgrade only.
Here is what I am thinking of doing.
Asume Node1 and Node2 are the current production SQL cluster nodes.
Node3 and Node4 are the new servers.
1. Move all cluster roles to Node1
2. Evict node2 from the cluster
3. Conect Node3 and join it to the cluster
4. Move all cluster roles to Node3
5. Evict Node1 from cluster
6. Connect Node4 and join it to the cluster
7. Connect Node3 and Node4 to the new SAN (while connected to the old SAN )
8. Setup Quorum and data stores in the new SAN
9. Move Quorum to the new SAN
10. Shutdown the SQL Server
11. Copy SQL DBs from old SAN to the new SAN. Change Drive letter mappings
to maintain the paths.
12. Disconnect old SAN connection completely.
13. Start SQL Server
Is this feasible ? Am I missing anything here ?
"Amila chandrasekera" <achandra@.insight.com> wrote in message
news:%23h6t5u7SHHA.412@.TK2MSFTNGP02.phx.gbl...
>I need your advise on migrating a two node SQL 2000 cluster to new hardware
>including servers and disks.
>
> thanks.
> Amila
>
|||Before eviting the nodes, you have to run the SQL installer to remove the
node from the SQL cluster configuration. You cn run it afterwards and force
it out, but that takes longer. You also have to run the installer and
install SQL to the new nodes. You then need to re-apply any service packs.
GNH
"Amila chandrasekera" <achandra@.insight.com> wrote in message
news:OGAFgGFUHHA.1212@.TK2MSFTNGP03.phx.gbl...
> Thanks for the replies so far. This migration is from SQL 2000 to SQL 2000
> (both source and target are running on Windows 2003 Advanced server). I am
> not planning to do a SQL 2005 upgrade with this migration. It is purely a
> hardware upgrade only.
> Here is what I am thinking of doing.
> Asume Node1 and Node2 are the current production SQL cluster nodes.
> Node3 and Node4 are the new servers.
> 1. Move all cluster roles to Node1
> 2. Evict node2 from the cluster
> 3. Conect Node3 and join it to the cluster
> 4. Move all cluster roles to Node3
> 5. Evict Node1 from cluster
> 6. Connect Node4 and join it to the cluster
> 7. Connect Node3 and Node4 to the new SAN (while connected to the old
> SAN )
> 8. Setup Quorum and data stores in the new SAN
> 9. Move Quorum to the new SAN
> 10. Shutdown the SQL Server
> 11. Copy SQL DBs from old SAN to the new SAN. Change Drive letter mappings
> to maintain the paths.
> 12. Disconnect old SAN connection completely.
> 13. Start SQL Server
> Is this feasible ? Am I missing anything here ?
>
> "Amila chandrasekera" <achandra@.insight.com> wrote in message
> news:%23h6t5u7SHHA.412@.TK2MSFTNGP02.phx.gbl...
>
|||How Can I remove SQL after evicting the node ?
"Geoff N. Hiten" <SQLCraftsman@.gmail.com> wrote in message
news:OQ5q9KFUHHA.1180@.TK2MSFTNGP05.phx.gbl...
> Before eviting the nodes, you have to run the SQL installer to remove the
> node from the SQL cluster configuration. You cn run it afterwards and
> force it out, but that takes longer. You also have to run the installer
> and install SQL to the new nodes. You then need to re-apply any service
> packs.
> GNH
>
> "Amila chandrasekera" <achandra@.insight.com> wrote in message
> news:OGAFgGFUHHA.1212@.TK2MSFTNGP03.phx.gbl...
>
|||Go ahead and run the installer on the remaining node. When you remove the
evicted node from SQL the installer will time out and isue a warning, but it
will remove it from the SQL configuration.
Geoff N. Hiten
Senior Database Administrator
Microsoft SQL Server MVP
"Amila chandrasekera" <achandra@.insight.com> wrote in message
news:e9erf1pVHHA.3568@.TK2MSFTNGP06.phx.gbl...
> How Can I remove SQL after evicting the node ?
> "Geoff N. Hiten" <SQLCraftsman@.gmail.com> wrote in message
> news:OQ5q9KFUHHA.1180@.TK2MSFTNGP05.phx.gbl...
>
|||You can also remove it manually, but the Best Practice is to use the SQL
Server setup instead.
http://support.microsoft.com/kb/290991/en-us
Sincerely,
Anthony Thomas
"Geoff N. Hiten" <SQLCraftsman@.gmail.com> wrote in message
news:O84Iu3qVHHA.4964@.TK2MSFTNGP06.phx.gbl...
> Go ahead and run the installer on the remaining node. When you remove the
> evicted node from SQL the installer will time out and isue a warning, but
it[vbcol=seagreen]
> will remove it from the SQL configuration.
>
> --
> Geoff N. Hiten
> Senior Database Administrator
> Microsoft SQL Server MVP
>
> "Amila chandrasekera" <achandra@.insight.com> wrote in message
> news:e9erf1pVHHA.3568@.TK2MSFTNGP06.phx.gbl...
the[vbcol=seagreen]
installer[vbcol=seagreen]
service[vbcol=seagreen]
migration.
>
including servers and disks.
thanks.
Amila
Create a new cluster with the new hardware, install a SQL instance, and then
migrate the databases over to the new instance (e.g. following steps in
http://vyaskn.tripod.com/moving_sql_server.htm and its referenced articles).
If the shared drives are presented from a SAN, you can remove the drives
from the cluster, create a new cluster, install a SQL instance in exactly the
same way as the existing SQL instance, and present the shared drives to the
new cluster.
If you can afford the downtime, and want to keep the server names, you can
remove the shared drives (LUNs), deactivate the cluster nodes, create a new
cluster with the same node names, cluster names, and virtual server names,
install a SQL instance, and present the same LUNs to the new cluster. The new
SQL instance can come up exactly the same as the previous one.
You may also try to perform the so-called rolling upgrade, i.e. upgrade one
node to new hardware a time.
Which method to choose depends on your upgrade requirements.
Linchi
"Amila chandrasekera" wrote:
> I need your advise on migrating a two node SQL 2000 cluster to new hardware
> including servers and disks.
>
> thanks.
> Amila
>
>
|||We have done both of what Linchi suggested: new system build/disk migration
versus node rebuild/upgrade.
The new cluster build is cleaner/easier, but then your applications have to
be migrated to the new host name (unless you can incur the long outage).
The node rebuild/upgrade is not quite as clean, but it minimizes the impact
to your end users.
Check out the maintenance and troubleshooting sections of the following
guide. There is also a link at the top that directs you to the 2005 doc as
well. Read both.
http://www.microsoft.com/technet/prodtechnol/sql/2000/maintain/failclus.mspx#E14AG
The short sequence is:
Uninstall passive node from the sql server setup.
Evict passive node from cluster administrator.
Rebuild passive node.
Join rebuilt node through cluster administrator.
Install rebuilt node to sql server setup.
Patch sql server rebuilt node to current patch + hotfix as active node.
Move over resources and repeat for each cluster node.
Sincerely,
Anthony Thomas
"Amila chandrasekera" <achandra@.insight.com> wrote in message
news:%23h6t5u7SHHA.412@.TK2MSFTNGP02.phx.gbl...
> I need your advise on migrating a two node SQL 2000 cluster to new
hardware
> including servers and disks.
>
> thanks.
> Amila
>
|||Run upgrade advisor to detect upgrade issues, run checkdb on the databases
on the clusters, detach them, copy them (do not move them) to the new
cluster, attach them, run checkdb, update statistics, back them up. Migrate
all dependencies (logins, jobs, extended stored procedures, com objects and
file paths).
Check all functionality on the new cluster. Roll back if you have to by
reattaching the existing database on the old cluster.
repoint the client applications.
You might want to review all methods to do this in the
http://download.microsoft.com/download/1/6/c/16c0ec7a-bb53-4aea-9020-cb2f80424322/SQL2005UpgradeTechRef.doc
Hilary Cotter
Looking for a SQL Server replication book?
http://www.nwsu.com/0974973602.html
Looking for a FAQ on Indexing Services/SQL FTS
http://www.indexserverfaq.com
"Amila chandrasekera" <achandra@.insight.com> wrote in message
news:%23h6t5u7SHHA.412@.TK2MSFTNGP02.phx.gbl...
>I need your advise on migrating a two node SQL 2000 cluster to new hardware
>including servers and disks.
>
> thanks.
> Amila
>
|||Thanks for the replies so far. This migration is from SQL 2000 to SQL 2000
(both source and target are running on Windows 2003 Advanced server). I am
not planning to do a SQL 2005 upgrade with this migration. It is purely a
hardware upgrade only.
Here is what I am thinking of doing.
Asume Node1 and Node2 are the current production SQL cluster nodes.
Node3 and Node4 are the new servers.
1. Move all cluster roles to Node1
2. Evict node2 from the cluster
3. Conect Node3 and join it to the cluster
4. Move all cluster roles to Node3
5. Evict Node1 from cluster
6. Connect Node4 and join it to the cluster
7. Connect Node3 and Node4 to the new SAN (while connected to the old SAN )
8. Setup Quorum and data stores in the new SAN
9. Move Quorum to the new SAN
10. Shutdown the SQL Server
11. Copy SQL DBs from old SAN to the new SAN. Change Drive letter mappings
to maintain the paths.
12. Disconnect old SAN connection completely.
13. Start SQL Server
Is this feasible ? Am I missing anything here ?
"Amila chandrasekera" <achandra@.insight.com> wrote in message
news:%23h6t5u7SHHA.412@.TK2MSFTNGP02.phx.gbl...
>I need your advise on migrating a two node SQL 2000 cluster to new hardware
>including servers and disks.
>
> thanks.
> Amila
>
|||Before eviting the nodes, you have to run the SQL installer to remove the
node from the SQL cluster configuration. You cn run it afterwards and force
it out, but that takes longer. You also have to run the installer and
install SQL to the new nodes. You then need to re-apply any service packs.
GNH
"Amila chandrasekera" <achandra@.insight.com> wrote in message
news:OGAFgGFUHHA.1212@.TK2MSFTNGP03.phx.gbl...
> Thanks for the replies so far. This migration is from SQL 2000 to SQL 2000
> (both source and target are running on Windows 2003 Advanced server). I am
> not planning to do a SQL 2005 upgrade with this migration. It is purely a
> hardware upgrade only.
> Here is what I am thinking of doing.
> Asume Node1 and Node2 are the current production SQL cluster nodes.
> Node3 and Node4 are the new servers.
> 1. Move all cluster roles to Node1
> 2. Evict node2 from the cluster
> 3. Conect Node3 and join it to the cluster
> 4. Move all cluster roles to Node3
> 5. Evict Node1 from cluster
> 6. Connect Node4 and join it to the cluster
> 7. Connect Node3 and Node4 to the new SAN (while connected to the old
> SAN )
> 8. Setup Quorum and data stores in the new SAN
> 9. Move Quorum to the new SAN
> 10. Shutdown the SQL Server
> 11. Copy SQL DBs from old SAN to the new SAN. Change Drive letter mappings
> to maintain the paths.
> 12. Disconnect old SAN connection completely.
> 13. Start SQL Server
> Is this feasible ? Am I missing anything here ?
>
> "Amila chandrasekera" <achandra@.insight.com> wrote in message
> news:%23h6t5u7SHHA.412@.TK2MSFTNGP02.phx.gbl...
>
|||How Can I remove SQL after evicting the node ?
"Geoff N. Hiten" <SQLCraftsman@.gmail.com> wrote in message
news:OQ5q9KFUHHA.1180@.TK2MSFTNGP05.phx.gbl...
> Before eviting the nodes, you have to run the SQL installer to remove the
> node from the SQL cluster configuration. You cn run it afterwards and
> force it out, but that takes longer. You also have to run the installer
> and install SQL to the new nodes. You then need to re-apply any service
> packs.
> GNH
>
> "Amila chandrasekera" <achandra@.insight.com> wrote in message
> news:OGAFgGFUHHA.1212@.TK2MSFTNGP03.phx.gbl...
>
|||Go ahead and run the installer on the remaining node. When you remove the
evicted node from SQL the installer will time out and isue a warning, but it
will remove it from the SQL configuration.
Geoff N. Hiten
Senior Database Administrator
Microsoft SQL Server MVP
"Amila chandrasekera" <achandra@.insight.com> wrote in message
news:e9erf1pVHHA.3568@.TK2MSFTNGP06.phx.gbl...
> How Can I remove SQL after evicting the node ?
> "Geoff N. Hiten" <SQLCraftsman@.gmail.com> wrote in message
> news:OQ5q9KFUHHA.1180@.TK2MSFTNGP05.phx.gbl...
>
|||You can also remove it manually, but the Best Practice is to use the SQL
Server setup instead.
http://support.microsoft.com/kb/290991/en-us
Sincerely,
Anthony Thomas
"Geoff N. Hiten" <SQLCraftsman@.gmail.com> wrote in message
news:O84Iu3qVHHA.4964@.TK2MSFTNGP06.phx.gbl...
> Go ahead and run the installer on the remaining node. When you remove the
> evicted node from SQL the installer will time out and isue a warning, but
it[vbcol=seagreen]
> will remove it from the SQL configuration.
>
> --
> Geoff N. Hiten
> Senior Database Administrator
> Microsoft SQL Server MVP
>
> "Amila chandrasekera" <achandra@.insight.com> wrote in message
> news:e9erf1pVHHA.3568@.TK2MSFTNGP06.phx.gbl...
the[vbcol=seagreen]
installer[vbcol=seagreen]
service[vbcol=seagreen]
migration.
>
Subscribe to: